CONSTRUCTION

DAMS

Cindere Dam and HEPP

The Cindere Dam and HEPP in Denizli has been constructed on the Greater Maeander River which is one of the major water resources in the region.

As a Roller Compacted Concrete (RCC) dam, Cindere Dam's body volume is 1.950.000 m3 and it has an irrigation capacity of it is 16.000 ha. Furthermore the dam's installed capacity is 30 MW and its produces 100 GWh per year.

Detail

Beydağ Dam

The dam constructed for irrigation purposes in Beydağ, İzmir is one of the Roller Compacted Concrete type dams as well.

The Beydağ Dam has been constructed across the Little Maeander River and its body volume is 2.700.000 m3 with an irrigation capacity of 22.000 ha.

Detail

Kiğı Dam and HEPP

The construction of the Kiğı Dam and HEPP across the Euphrates River within the provincial borders of Bingöl Province almost completed with a physical completion rate of 99%.

The dam having a height of 175 m is ranked 4th amount its class and it ranked 8th among all te dams in Turkey.

Detail

Al-Wehdah Dam

The Al- Wehdah Dam, which is one of the very successful projects of by Özaltın Construction, was constructed across the Yarmouk River in Jordan.

As a Roller Compacted Concrete dam, its body volume is 1.480.000 m3. The Al- Wehdah Dam was constructed to serve as a water source for Jordan, a country with limited sources of water.

Detail

Sawalkot Dam and HEPP

The Sawalkot Dam and HEPP, which is located in India, is being constructed across the Chenab River. As a Roller Compacted Concrete dam, the Sawalkot Dam's body volume is 1.885.000 m3.

The dam is constructed for power generation. It has an installed capacity of 1.906 MW and its total annual power generation capacity is intended to be 7.998 GWh when completed.

Detail

Özlüce Dam and HEPP

The Özlüce Dam and HEPP, which is near the Elazığ - Bingöl border, was constructed across the Euphrates River.

As a Clay Core Rock Fill dam, Özlüce Dam's body volume is 15.000.000 m3. The dam was constructed for power generation. It has an installed capacity of 200 MW and its total annual power generation capacity is 600 GWh. The Özlüce Dam and HEPP was completed in 1999 and it is one of the major power- generating dams in the region.

Detail

Koçköprü Dam and HEPP

The Koçköprü Dam and HEPP was Özaltın Construction's first dam project and it was constructed across the Zilan River.

Detail

Köprü Dam and HEPP

The Köprü Dam, which was constructed by the consortium where Özaltın Construction has 50% of the shares, was constructed on the Seyhan River in Adana.

Detail

Menge Dam and HEPP

The Menge Dam, which was constructed by the consortium where Özaltın Construction has 50% of the shares, was constructed on the Seyhan River in Adana.

Detail

Souktleta Dam

The Souktleta Dam, which will be constructed by the consortium where Özaltın Construction holds 40% of the shares, is in Algeria.

Detail

Savrun Dam and HEPP

The project seeing the signing of the contract in May 2017 is due completion in 2020.

Detail